La Center's Second Downtown Begins by Saving What Was Already There

"Everyone." That was the one-word answer an uncle of Eddie Barnhart gave when someone asked who used to swim at the family's hole on the East Fork Lewis River. Mayor Tom Strobehn retold the story at the September 17 groundbreaking for Downtown 2.0, as The Reflector reported.

The story matters because it describes the first phase. Six weeks after the shovels went in, the work on the property west of NW Pacific Highway along West Fifth Street is mostly about keeping things. That means trees, old timber, and a 1912 homestead the city plans to turn into a museum. The commercial space and housing in the plan come later. How much later depends on money the city doesn't have yet.

A homestead first, then a downtown

The Barnhart family bought this land in 1912. They raised cattle and harvested apples there, and the river swimming hole became a gathering place for the whole town, according to Clark County Today's republication of The Reflector's groundbreaking story. Downtown 2.0 is meant to bring that kind of gathering back, at a larger scale and with more uses.

Here is what the city has described for the site:

  • Commercial space and housing. Public Works and Planning Director Tracy Coleman said the goal is to expand the current downtown and "specialize in services that big chains cannot offer."
  • A plaza and river overlook. The Reflector's groundbreaking photos show the East Fork Lewis River from the spot where the overlook and plaza are planned.
  • A forested recreation area. Plans call for family-friendly trails, picnic areas, and an ADA-accessible boardwalk running from the future plaza into the woods, linking the new downtown to the existing core and the river.
  • An open museum in the original homestead. The mayor said it will hold historical artifacts, family records, and items dating back to the 1800s.
  • Reclaimed barn wood. Material from the barn and tool shed will be stored and reused in the community center.

Three of those five items are about preserving the land or its history. That share explains what is happening on the site this fall.

What is actually moving on the site

Two kinds of work have started, and neither one puts up a building.

The first is in the forest. Coleman said the environmental work already underway focuses on tree canopy management, native plant recruitment, habitat diversity, and erosion control. City staff led tours of the future urban forest trails at the groundbreaking. Since then, the site has been closed to the public because of active construction and heavy machinery. The city says it will announce when recreational access opens. No opening date has been given, so anyone hoping to walk the trails this winter should wait for that announcement.

The second is salvage. On the City of La Center's project bids page, a Downtown 2.0 deconstruction and salvage contract was open for bids until October 26 at 2 p.m. The scope covers salvaging material from three buildings, disposing of debris, and covering the stored material. That stored material is the wood the mayor said will go into the community center. Taking the old structures apart comes first, and the city plans to reuse that wood in what gets built afterward.

Why the order looks like this

The money sets the order. Mayor Strobehn said the city received $400,000 in state capital budget funding to launch Downtown 2.0, and that "we still have a $3.5 million funding gap to close in order to fully realize this project and build out the infrastructure La Center needs," as Clark County Today reported.

The size of that $400,000 makes more sense next to the planning-level estimates in the city's adopted Downtown 2.0 subarea plan from June 2025. These are early estimates and may have changed since the plan was written.

Planned piece 2025 planning estimate Plan timing
Plaza-related streetscape $297,000 Short term, within 3 years
Moving and reconstructing the historic house as a museum $310,000 Short term, within 3 years
River boardwalk $807,500 Medium term, 3 to 6 years

The two short-term items add up to $607,000 in those estimates. That is already more than the state appropriation, and the boardwalk alone would cost about twice the $400,000. These figures are separate line items, not a full project budget, but they show why the city placed the boardwalk in the three-to-six-year window. They also show why forest work and salvage, the lower-cost tasks that protect the site, could start as soon as the city broke ground.

The funding gap is old news to anyone who followed the purchase. In June 2025, The Reflector reported that the city council had authorized the mayor to negotiate a land purchase capped at $4 million or appraised value, whichever was lower, paid with real estate excise tax and park impact fee revenue. The city had asked the state for $4 million and received $400,000. State Sen. John Braun said at the groundbreaking that a community with consensus and a plan has an easier time seeking state support. The next state budget cycle will help decide how quickly the plaza and boardwalk move from estimates to construction.

Where residents have a say right now

The architecture is still open for comment. At the groundbreaking, visitors marked their three favorite architectural styles for the development. Coleman said the first of three planned design open houses was set for October 13 at 6:30 p.m. at City Hall, after the planning commission meeting. Two more are still ahead. The City of La Center website is the place to watch for those dates.

Coleman's stated goal is to grow the downtown "while maintaining the character of La Center." The remaining open houses are where residents can weigh in on what that character should look like.

The streets around it are changing too

Downtown 2.0 is one of several projects changing how people get around town over the next year. Two of them affect daily routes more directly.

4th Street and Brezee Creek. The city's project update says reconstruction of 4th Street between Cedar Avenue and Highland Road began June 15, with completion expected in December 2027. A two-lane bypass carries traffic while a new bridge goes in over Brezee Creek. The work zone speed limit is 20 mph, and flaggers run periodic daytime single-lane closures. Access to East Stonecreek Drive from East 4th Street is closed for the whole project, with a detour by way of 5th Street. When the work is done, 4th Street will have a continuous sidewalk on the north side and a 10-foot shared-use path for bikes and pedestrians on the south side. The creek will also allow safe passage for fish and wildlife.

The Pacific Highway path. This is a separate project: a 10-foot-wide concrete shared-use path, about 1,900 feet long, from NW Larsen Drive to the existing sidewalk at Kays Subdivision. It includes ditch regrading and a gravity wall near Jenny Creek. The city's engineering request anticipated construction starting October 1, with a goal of finishing in December 2026. Funding comes from the Transportation Improvement Board, federal transportation programs, and Move Ahead Washington.

Put together, these projects add walking routes on both sides of the old downtown, while the forest trails on the Barnhart site wait for their opening announcement.

The old downtown in the meantime

The existing core on Fourth Street has gained a few places to stop this year. The Sweet Collective, Tracy Coiteux's dessert and coffee shop at 103 E. Fourth St. across from Sternwheeler Park, opened in April in the former Trellis building. It serves local ice cream, coffee, baked goods, and house-made drinks. Legacy Park opened downtown in July. The La Center Farmers Market finished its Sunday season there on October 25.

Those spots are the downtown that Downtown 2.0 is meant to extend. The next step on the Barnhart land the public will see is the city's notice that the forest trails are open.

If you'd like to know how projects like Downtown 2.0 and the 4th Street rebuild might affect your street or a home you're considering, The Pettet Group follows these plans closely and is happy to walk through them with you. Let's Connect.

Your Story Deserves Thoughtful Representation

Partner with Husten and Brandy for a real estate experience grounded in care, communication, and local understanding. Whether you are buying, selling, relocating, or planning for the future, The Pettet Group is ready to help you move forward with confidence.

Follow Me on Instagram