This year, Clark County's park work in Felida started with sidewalks. The county is building curb, gutter and sidewalk along Northwest 16th Avenue in front of the Cougar Creek Woods property, and along Northwest 21st Avenue in front of the Foley Orchards property. Both properties are future county parks. The parks behind those sidewalks are still years away. The county's current plan doesn't call for construction at Cougar Creek Woods until 2031.
So for now, Felida's newest public space is a strip of concrete along a road. Its newest place to play is a cricket pitch at the park the neighborhood already has.
What went in along NW 16th and NW 21st
Both frontage jobs are on one county contract. Bids opened May 26, 2026, and the work went to DeWitt Construction for $287,956. County mailers dated July 2026 described the work at each site:
- Cougar Creek Woods, NW 16th Avenue: curb, gutter, stormwater and sidewalk improvements to connect with the existing sidewalk north and south of the property, plus a driveway cut for a future parking lot.
- Foley Orchards, NW 21st Avenue: curb, gutter, stormwater and sidewalk improvements to match the existing sidewalk on either side of the property. The Foley mailer says park planning and construction there are still several years off.
The Cougar Creek Woods work came from neighbors. In a June 29, 2026 reply to a resident's comment on the draft capital plan, county parks staff said the NW 16th sidewalk was being built "in response to several community requests to address the gap in sidewalk at this site." Staff added that the work would fix a grade problem at the north end of the frontage. The reply appears in the county's July 14, 2026 Parks Advisory Board minutes. It gave a start "sometime in July, 2026" and a finish "by the end of September." As of late October, the county's park projects page still describes both frontage jobs as under construction.
That driveway cut on 16th is the clearest sign of a future park at Cougar Creek Woods. It's an entrance to a parking lot that hasn't been designed yet.
Why the woods stay the way they are
If you've walked the informal paths in Cougar Creek Woods, the same June reply explains why they won't be getting gravel or signs anytime soon. The wooded part of the property has a habitat designation. Spreading gravel on the existing paths would need a permit, and turning those community-made trails into formal park trails would need a shoreline permit. Staff wrote that the informal trails affect the habitat and will have to be formalized and mitigated when the park is built. They also said the county won't add any new paths before the council adopts a park plan:
"We can't develop any park infrastructure without going through the required environmental and land use review process."
There is an older plan. The county drew up a site plan for Cougar Creek Woods in 2015, but the council never adopted it. Staff said they had meant to reopen it with public outreach for several years, but major maintenance work kept pulling staff away. Work on the property so far has been small: fencing along the cleared part of the site, planned in a July 2024 mailer, and a day of engineering testing announced in a November 2024 mailer.
The calendar the county has on paper
The schedule below combines the June 29 staff reply with the county's May 2026 draft of its 2027–2032 Parks Capital Improvement Plan.
| Year | Step at Cougar Creek Woods | Proposed in the 2027–2032 draft plan |
|---|---|---|
| 2028 | Revise and adopt the master plan | $160,000 |
| 2029 | Design and permitting | $240,000 |
| 2030 | Design and permitting | No amount listed |
| 2031 | Build the first phase of the park | $3.5 million |
These figures are proposals. The plan was still a draft when the Clark County Council scheduled a public hearing on the parks capital plan for November 3, 2026.
The previous draft, the 2026–2031 plan dated October 15, 2025, set aside $400,000 for Cougar Creek Woods in 2026 and $4.3 million over six years. According to the June reply, money budgeted for the property in 2024, 2025 and 2026 was never spent. Unspent money doesn't disappear. It stays in the park impact fee account for PIF District 9, the district that includes Cougar Creek Woods. By law, those funds have to go to facilities that serve that district.
Foley Orchards is less settled. The 2026–2031 draft gave it $200,000 as a future neighborhood park, but the 2027–2032 draft has no development budget line for it. For now, the new sidewalk on NW 21st is the main county work there.
Another project runs alongside the park. The Columbian reported in June on a planned restoration of about half a mile of Cougar Creek, south of 119th Street and through Cougar Creek Woods. Construction is planned for 2028, and the county was applying for a $975,000 state grant to pay for it. The paper described a bigger trail system as a possibility down the road, and the county hasn't committed to one.
What Felida can use this November
While the new parks are on hold, the existing ones are where things are happening.
A cricket pitch at Felida Community Park
The Columbian reported in June that construction was nearly finished on Clark County's first public cricket practice pitch, at the north end of Felida Community Park off Northwest 127th Street. The county's park page now lists it as open to the public during park hours, first come, first served. Players are asked to keep it to an hour when others are waiting.
The park is at 3798 NW 122nd St. and covers 15.13 acres. It opened in 2003, and the inclusive play area and a 35-stall parking lot were added in 2023. It also has two full-size soccer fields used by Salmon Creek Soccer Club, a mini soccer field, and close to three-quarters of a mile of paved paths. Hours are 7 a.m. to dusk.
The picnic shelter is free for the winter
From November 1 through March 31, every county picnic shelter is free and first come, first served. That includes Felida's, which seats 50 under cover. From April through October, the shelter rents for $85.
The Cougar Creek Trail
You can already walk along the creek. The county's existing Cougar Creek Trail is a half-mile, six-foot-wide crushed-gravel path from NW 119th Street to the Salmon Creek Trail.
Where the next decisions get made
The steps between a sidewalk and a finished park will each happen in public, and each one has a way for neighbors to take part:
- The Felida Community Neighborhood Association. The association was founded in 1997 and has recently restarted. There are no dues, and anyone who lives, owns property or runs a business inside its boundaries is automatically a member. The agenda for its October 29 meeting, the last one of 2026, listed a Cougar Creek Woods update from Clark County Parks and an update from Public Works on the Neighborhood Traffic Management Program. The October postcard lists [email protected] as the association's contact.
- The county's capital plan. The council scheduled a November 3 public hearing on the parks capital plan, the step on the way to turning the draft dollar figures into an adopted plan. The hearing notice is posted on the county's site.
- The Cougar Creek Woods master plan. The county's property page says neighbors will be invited to community surveys, open houses and a public comment period. They'll also get to suggest a new name for the park. Questions go to [email protected] or 564.397.2285.
On the county's draft schedule, the 2028 master plan is when Felida will help decide what the woods behind the new sidewalk become.
If the county's long park timeline has you wondering how plans like these play out on your own street, The Pettet Group is happy to talk it through. We follow these projects because we live here too. Let's Connect.